Preparation of the Application Projects for Zile Wastewater Treatment Plant
It covers the preparation of implementation projects for the Zile Wastewater Treatment Plant, which will serve a population equivalent of 62,940 and has a design flow of 6,913 m³/day. Within the scope of the project, the process, architectural, reinforced concrete, mechanical, and electrical projects of the treatment plant have been revised in accordance with the technical opinions of the Provincial Bank. Additionally, an energy transmission line project related to the transformer planned to have a power of 1250 kVA has been prepared to meet the facility’s energy needs; a ground survey including drilling work with a depth of 110 m aimed at the plant area has been conducted. Within the scope of the project, quantity tables have been prepared and a bill of quantities has been created according to the 2014 Unit Prices, completing the necessary documentation for implementation.
Within the scope of this project, the following services have been provided by our staff:
Creation of a process design suitable for a population equivalent of 62,940 and a design flow rate of 6,913 m³/day, and revision of existing projects,
Preparation of architectural, reinforced concrete, mechanical, and electrical application projects and updating them according to the opinions of the Municipal Bank,
Preparation of the energy transmission line project for the facility transformer with a capacity of 1250 kVA,
Conducting and evaluating ground survey works that include drilling down to a depth of 110 m,
Preparation of quantity tables for all units,
Creation of the bill of quantities according to 2014 Unit Prices and preparation of the project's financial analyses,
Completion of the technical reports and project documents that are essential for implementation.